Project Profile

ASU Tunnel Network 015A

Project profile for Viking Specialty Contracting environmental work in Tempe, Arizona.

Mechanical ductwork at ASU Tunnel Network 015A
ASU Tunnel Network 015A, Tempe, Arizona

Project Overview

Controlled environmental work planned around a underground utility tunnel.

Viking performed environmental contracting services for Arizona State University in Tempe, Arizona. The project is tagged for Colleges & Universities; Utilities/Infrastructure and supports the TSI pipe insulation removal; glove bag removal; manifest/waste handling; closeout documentation service categories.

Location
Tempe, Maricopa County
Facility
Underground utility tunnel
Scope
TSI pipe insulation removal; glove bag removal; manifest/waste handling; closeout documentation

Services Documented

  • TSI pipe insulation removal
  • glove bag removal
  • manifest/waste handling
  • closeout documentation

Materials / Conditions

  • Thermal system insulation (TSI)

Project Semiconductorligence

Project details corporate clients need to evaluate the work.

Project ID
V22-172
Client/Public Name
Arizona State University
City
Tempe
County
Maricopa
Industry
Colleges & Universities; Utilities/Infrastructure
Building Type
Underground utility tunnel
Schedule
2022-03-23 - 2022-04-13
Public Use
Use with permission / public institution

Project Challenge

Protect the facility while the work moved through regulated conditions.

The work required coordination, containment, safety planning, and documentation appropriate for a underground utility tunnel environment.

Viking Response

Contain the work. Protect the facility. Support the next phase.

Services documented for this project include: TSI pipe insulation removal; glove bag removal; manifest/waste handling; closeout documentation. Materials/work areas included: Thermal system insulation (TSI).

Frequently Asked Questions

What asbestos work was performed in the ASU tunnel network?

The documented scope included thermal system insulation removal, glove-bag removal, regulated waste handling, manifests, and closeout documentation.

Why is glove-bag work useful in a utility tunnel?

Glove-bag methods can isolate a focused section of pipe insulation and help control fiber release when work is performed under the approved project procedures.

How are underground tunnel conditions managed?

Tunnel work requires controlled access, task-specific containment, respiratory and personal protection, careful waste movement, and coordination around university utility operations.

What documentation is important after TSI removal?

Closeout documentation can include waste manifests, work records, project photographs, clearance information, and records needed by the owner and consultant.